Skip to main content

Week 3 (June 19-23)

The process of renovating  the wayside power rails began this week.  The previous way of connected the copper wayside power rails is shown in Figure 1.  One of the problems is that the position of the overlapping is not consistent throughout each joint on the half-scale model.  Therefore, the collector shoe could glide from a higher rail to a lower rail at one joint, but glide from a lower to higher rail at another joint.  The collector shoe is unable to glide from a lower to higher copper rail because the shoe would crash into the joint and prevent it from gliding.  In addition, the screw at each joint sticks out just enough to get the shoe caught on the screw even with the modified collector shoes.


Figure 1:  Original way of joining together the copper rails.  (Drawn by Tan Ho)


The original design of the wayside power rails is retained as much as possible to decrease the amount of time needed to renovate the power rails.  The prior design that consisted of overlapping the copper rails at the joints is kept to avoid the need to remove all the copper rails from the PVC pipes.  However, the overlapping position is changed according to the direction that the collector shoe will glide.  The goal is to get the collector shoe to only glide from a higher copper rail to a lower copper rail at each joint, which is shown in Figure 2.  The arrow indicates the direction that the collector shoe glides.  A slightly larger drill bit is also used to countersink the existing holes on the copper rails.  The result is screws that are flush with the surface of the copper rail.


Figure 1:  Direction that the collector shoes glide.  (Drawn by Tan Ho)

Comments

Popular posts from this blog

Week 8 (July 24-28)

The design for the collector shoe guides had been changed slightly.  The outer lip, or wall, on the guide is not needed.  We realized that the collector shoes do not hang lower than the guide.  In addition,  the curves on the guide that push the collector shoes into position are difficult to create.  Instead, extra wheels that the bogie team no longer needed were used in place of the curves.  We also spent this week writing the majority of the final report.

Week 9 (July 31 - August 4)

One of the collector shoe guides have been built and installed to an end of the track.  The installed collector shoe guide is shown in Figure 1.  The collector shoes slide between the wheels and into the wayside power rails.  Wires connecting to the battery have also been installed to the rails.  Wires from the previous Wayside Power Team are reused.  The ends of the wires are repaired where needed and zip ties are used to keep the wires organized on the track.  A multimeter is placed at the other end of the rails to ensure that the transfer of electricity through the wayside power rails is successful.  We have also finished the final report this week. Figure 1:  Installed collector shoe guide. (Photo by Kevin Leong) Figure 2:  Fixing and organizing wires. (Photo by Kevin Leong)

Week 7 (July 17-21)

By the end of this week, all of the wayside power rails have been installed for the half-scale track.  Guides for the collector shoes need to be installed at the ends of the wayside power rails.  The purpose of a guide to gently feed a freely dangling pair of collector shoes back into a pair of wayside power rails.  This occurs during a track change, in which a pair of collector shoes derails from the wayside power rails on one side of the track.  Another pair of collector shoes needs to be guided back into the wayside power rails on the other track.  We brainstormed ideas for how the collector shoe guides should be made.  Tan was able for draw out a model of the guide using SolidWorks, as shown in Figure 1. Figure 1:  Model of a collector shoe guide. (Drawn by Tan Ho)