Skip to main content

Week 3 (June 19-23)

The process of renovating  the wayside power rails began this week.  The previous way of connected the copper wayside power rails is shown in Figure 1.  One of the problems is that the position of the overlapping is not consistent throughout each joint on the half-scale model.  Therefore, the collector shoe could glide from a higher rail to a lower rail at one joint, but glide from a lower to higher rail at another joint.  The collector shoe is unable to glide from a lower to higher copper rail because the shoe would crash into the joint and prevent it from gliding.  In addition, the screw at each joint sticks out just enough to get the shoe caught on the screw even with the modified collector shoes.


Figure 1:  Original way of joining together the copper rails.  (Drawn by Tan Ho)


The original design of the wayside power rails is retained as much as possible to decrease the amount of time needed to renovate the power rails.  The prior design that consisted of overlapping the copper rails at the joints is kept to avoid the need to remove all the copper rails from the PVC pipes.  However, the overlapping position is changed according to the direction that the collector shoe will glide.  The goal is to get the collector shoe to only glide from a higher copper rail to a lower copper rail at each joint, which is shown in Figure 2.  The arrow indicates the direction that the collector shoe glides.  A slightly larger drill bit is also used to countersink the existing holes on the copper rails.  The result is screws that are flush with the surface of the copper rail.


Figure 1:  Direction that the collector shoes glide.  (Drawn by Tan Ho)

Comments

Popular posts from this blog

Week 9 (July 31 - August 4)

One of the collector shoe guides have been built and installed to an end of the track.  The installed collector shoe guide is shown in Figure 1.  The collector shoes slide between the wheels and into the wayside power rails.  Wires connecting to the battery have also been installed to the rails.  Wires from the previous Wayside Power Team are reused.  The ends of the wires are repaired where needed and zip ties are used to keep the wires organized on the track.  A multimeter is placed at the other end of the rails to ensure that the transfer of electricity through the wayside power rails is successful.  We have also finished the final report this week. Figure 1:  Installed collector shoe guide. (Photo by Kevin Leong) Figure 2:  Fixing and organizing wires. (Photo by Kevin Leong)

Week 8 (July 24-28)

The design for the collector shoe guides had been changed slightly.  The outer lip, or wall, on the guide is not needed.  We realized that the collector shoes do not hang lower than the guide.  In addition,  the curves on the guide that push the collector shoes into position are difficult to create.  Instead, extra wheels that the bogie team no longer needed were used in place of the curves.  We also spent this week writing the majority of the final report.

Week 2 (June 12-16)

Several pairs of current collectors were available for us to use.  The current collectors are mounted on the bogie and used to pick up the electricity from the wayside power rails.  The current wayside power rails are made by hot-gluing and screwing copper rails into cut-open PVC pipes that serve as insulation.  However, this design of the power rails does not create a smooth enough power rail for the current collector to glide along.  The company that manufactured the current collectors, Kyec, also sells insulated copper rails that were made specifically for the Kyec current collectors to easily glide through.  However, due to the expensive cost and the great amount of time it would take for delivery, we decided to figure out a way to fix the existing power rails.  The main reason why the power rails are not smooth enough is because of how the copper rails are connected at the joints. Two copper rails are overlapped and a single screws holds both rails tog...